Butler St & 7th Ave Construction - Week of March 2nd to March 6th
This week, crews will be working along Butler and Forest Streets and 7th Ave. Here’s what to expect from Monday (3/2) to Friday (3/6):
A crew will continue work along Butler and Forest Streets and 7th Ave, working on swales and laying sod.
There may be daytime lane closures on Butler Street between 6th and 7th Avenues and on 7th Ave between “Dirt” Main Street and Butler Street.
Please allow extra travel time and drive safely! Thank you for being so patient!

Bessie St, East Blvd, 8th & 9th Aves. Construction Week of March 2nd to March 6th.
Crews will be installing a concrete curb along Bessie and 8th Ave, grading roads, and installing new shell road material. Here’s what to expect from Monday (3/2) to Friday (3/6):
- Installation of concrete curb on Bessie and 8th Ave.
- Grading of roads and installation of new shell road material on 8th Avenue between Main Street and East Blvd; on East Blvd from 9th to 8th Avenues; and Oakdale Street between 8th and 10th Avenues.
8th Avenue between East Blvd and Bessie Street and Bessie Street between 7th and 8th Avenues may have temporary daytime closures.
Please allow extra travel time and drive safely! Thank you for your patience!

West 2nd Avenue Construction Week of March 2nd to 6th
The information below is for West of Pine Street
Please be sure to allow for extra travel time!
Crews will be installing lime rock and curbs, repairing concrete and paver driveways, and removing old asphalt and installing lime rock for paving. Here’s what to expect:
• Monday (2/2) – Friday (2/6)
- From 727 to 806 W. 2nd Ave, crews will be grading lime rock to prepare for paving.
- From 914 to 1141 W. 2nd Ave, crews will be installing lime rock base material for curbs, and forming and pouring concrete curb. Crews will work with residents to notify them 24 hours in advance when they will lose access to their driveways.
- Tie-in paver and concrete driveways to the new curb where needed.
• Thursday (2/5) – Friday (2/6)
- From 1141 to 914 W. 2nd Ave, crews will be installing lime rock base in preparation for paving.
Daytime closures will be in effect. Please drive carefully! Thank you for your continued patience!

“Yard Waste Awareness”
Yard clippings and leaves don’t belong in storm drains. They can clog drains and add excess nutrients to our lakes, causing algae blooms.
Compost or bag yard waste properly!
For more information, visit our Stormwater Page: https://www.town.windermere.fl.us/page/stormwater
#NPDES #ProtectOurLakes

Our Food Trucks are fired up, flavors are sizzling, and your favorite bites are waiting just for you.
Grab your umbrella, bring your appetite, and treat yourself!
Tonight @ Town Square
From 5:30 to 9:30 PM
February Food Truck Night: Mark your calendars and bring your appetite! 🌮🍔🌯
Join us on Friday, February 27th, from 5:30 PM to 9:30 PM at Town Square Park for a night of great food, family fun, and music under the stars.
Enjoy a variety of delicious food trucks offering something for everyone — whether you’re craving sweet, savory, or somewhere in between.
✨ Special participation by the Windermere Library with crafts for the whole family and live music by Mauro Augustto!
Bring your friends, family, and lawn chairs, and come enjoy a wonderful evening in our beautiful Town!
We look forward to seeing you there!

West 2nd Avenue Construction Week of Feb. 23 to Feb. 27
The information below is for West of Pine Street
Please be sure to allow for extra travel time!
Crews will be installing lime rock and curbs, repairing concrete and paver driveways, and removing old asphalt and installing lime rock for paving. Here’s what to expect from Monday (2/23) to Friday (2/27):
From 727 to 800 W. 2nd Ave, crews will be removing old asphalt and dirt and installing new lime rock for paving.
From 914 to 1141 W. 2nd Ave, crews will be installing lime rock base material for curbs and forming and pouring concrete curbs. Crews will work with residents to notify them 24 hours in advance when they will lose access to their driveways.
Tie-in paver and concrete driveways to the new curb where needed.
Crews will be grading lime rock.
Daytime closures will be in effect. Please drive carefully!
Thank you for your continued patience!

Bessie St, East Blvd, 8th & 9th Aves. Construction Week of Feb. 23 to Feb. 27
Crews will be installing storm drainage, grading roads, and installing new shell road material. Here’s what to expect from Monday (2/23) to Friday (2/27):
Installation of Storm Drainage on 8th Ave from Magnolia to East Blvd. and on Bessie between 8th Ave and 7th Ave.
Grading of roads and installation of new shell road material on 8th Avenue between Main Street and East Blvd; on East Blvd from 9th to 8th Avenues; and Oakdale Street between 8th and 10th Avenues.
8th Avenue between East Blvd and Bessie Street and Bessie Street between 7th and 8th Avenues will be closed this week!
Please allow extra travel time and drive safely! Thank you for your patience!

Butler St & 7th Ave Construction - Week of Feb. 23 to Feb. 27
This week, crews will be working along Butler and Forest Streets and in Fernwood Park. Here’s what to expect from Monday (2/23) to Friday (2/27):
- A crew will continue work along Butler and Forest Streets as well as Fernwood Park, grading roads, working on swales, and laying sod.
There may be daytime lane closures on Butler Street between 6th and 7th Avenues and on 7th Ave between “Dirt” Main Street and Butler Street.
Please allow extra travel time and drive safely! Thank you for being so patient!

February Food Truck Night: Mark your calendars and bring your appetite! 🌮🍔🌯
Join us on Friday, February 27th, from 5:30 PM to 9:30 PM at Town Square Park for a night of great food, family fun, and music under the stars.
Enjoy a variety of delicious food trucks offering something for everyone — whether you’re craving sweet, savory, or somewhere in between.
✨ Special participation by the Windermere Library with crafts for the whole family and live music by Mauro Augustto!
Bring your friends, family, and lawn chairs, and come enjoy a wonderful evening in our beautiful Town!
We look forward to seeing you there!

🎾 Tennis Courts Closure Notice 🎾
Please note that the Main Street Tennis Courts will be closed starting Monday, February 23, for resurfacing. The project is expected to take several days to complete.
The courts will not be available during this time. Please plan accordingly and avoid the area while work is underway.
Thank you for your patience as we make improvements to enhance your playing experience!

Commissioner Wilson – In-Person Office Hours!
Have a question, concern, or idea you’d like to share? This is your opportunity to connect directly during in-person office hours.
📅 Thursday, February 19
From 11:30 AM to 3:00 PM
@ PD/Community Conference Room
Reserve your time slot today:
📞 Call (407) 836-7312
📧 Email district@ocfl.net
Schedule your appointment and make your voice heard!


West 2nd Avenue Construction Week of Feb. 16 to 20.
The information below is for West of Pine Street
Please be sure to allow for extra travel time!
Crews will be installing lime rock and curbs, repairing concrete and paver driveways, and removing old asphalt and installing Lime rock for paving. Here’s what to expect from Monday (2/16) – Friday (2/20):
From 636 to 800 W. 2nd Ave, two crews will be removing old asphalt and dirt and installing new lime rock for paving.
From 914 to 1141 W. 2nd Ave, crews will be installing lime rock base material for curbs and forming and pouring concrete curbs. Crews will work with residents to notify them 24 hours in advance when they will lose access to their driveways.
Tie-in paver and concrete driveways to the new curb where needed.
Daytime closures will be in effect. Please drive carefully! Thank you for your continued patience!

Butler St & 7th Ave Construction - Week of Feb. 16th – Feb. 20th.
This week, crews will grade Butler and Forest Streets and work in Fernwood Park. Here’s what to expect from Monday (2/16) to Friday (2/20):
A crew will continue work on Butler and Forest Streets, as well as at Fernwood Park, grading roads, working on swales, and laying sod.
There could be daytime closures on Butler Street between 6th and 7th Avenues and on 7th Ave between “Dirt” Main Street and Butler Street.
Please allow extra travel time and drive safely! Thank you for being so patient!

Bessie St, East Blvd, 8th & 9th Aves. Construction Week of Feb 16th – Feb 20th
Crews will be installing storm drainage, grading roads, and installing new shell road material. Here’s what to expect from Monday (2/16) to Friday (2/20):
Installation of Storm Drainage on 8th Ave from East Blvd. to Bessie Street and on Bessie between 8th Ave and 7th Ave.
Grading of roads and installation of new shell road material on 8th Avenue between Main Street and East Blvd; on East Blvd from 9th to 8th Avenues; and Oakdale Street between 8th and 10th Avenues
8th Avenue between East Blvd and Bessie Street and Bessie Street between 7th and 8th Avenues will be closed this week.
There may be travel delays in this area, so PLEASE allow extra travel time and drive safely! Thank you for your patience!

February Food Truck Night: Mark your calendars and bring your appetite! 🌮🍔🌯
Join us on Friday, February 27th, from 5:30 PM to 9:30 PM at Town Square Park for a night of great food, family fun, and music under the stars.
Enjoy a variety of delicious food trucks offering something for everyone — whether you’re craving sweet, savory, or somewhere in between.
✨ Special participation by the Windermere Library with crafts for the whole family and live music by Mauro Augustto!
Bring your friends, family, and lawn chairs, and come enjoy a wonderful evening in our beautiful Town!
We look forward to seeing you there!

Lakes Cleanup Day – Round 2
Sunday, April 19, 2026 | 1:30 – 3:30 PM
Help us keep Windermere’s lakes pristine!
After our first Lakes Cleanup Day on November 2, here’s your chance to join us for Round 2!
Meeting Location: Fernwood Park, 632 Butler Street
Time: 1:15 PM (to gather supplies and organize teams)
What to Bring: Closed-toed shoes; be prepared to walk through neighborhoods collecting trash to prevent litter from entering our lakes.
This is a great activity for the whole family—minors must be accompanied by an adult.
To register: Use the link or QR code on our website and social media.
For more information, contact Peter Balgobin.
#CleanLakes #LakesCleaupDay #Windermere #Stormwater #NPDES

Bessie St, East Blvd, 8th & 9th Aves. Construction Week of Feb 9 to Feb 13
Crews will be installing storm drainage. Here’s what to expect from Monday (2/9) - Friday (2/13):
Installation of Storm Drainage on 8th Ave from East Blvd. to Bessie Street and on Bessie between 8th Ave and 7th Ave.
Grading of roads and installation of new shell road material on 8th Avenue between Main Street and East Blvd; on East Blvd from 9th to 8th Avenues; and Oakdale Street between 8th and 10th Avenues
8th Avenue between East Blvd and Bessie Street and Bessie Street between 7th and 8th Avenues will be closed this week.
Please allow extra travel time and drive safely! Thank you for your patience!

West 2nd Avenue Construction Week of Feb. 9 to 13.
The information below is for West of Pine Street
Please be sure to allow for extra travel time!
Crews will be installing lime rock and curbs, repairing concrete and paver driveways, and removing old asphalt and installing Lime rock for paving. Here’s what to expect:
• Monday (2/9): Installation of curb on south side of street. 706 W 2nd Ave.
• Monday (2/9) – Friday (2/13):
- Two crews removing old asphalt and dirt and installing new lime rock for paving. From 535 to 636 W 2nd Ave and from 802 to 732 W 2nd Ave.
- Tie-in paver and concrete driveways to new curb.
• Tuesday (2/10) – Friday (2/13):
- Installation of lime rock Base material for ribbon curb in cul de sac.
- Form and pour concrete ribbon curb in cul de sac.
- Crews will work with residents to notify them 24 hours in advance when they will lose access to their driveway.
Daytime closures will be in effect. Please drive carefully! Thank you for your continued patience!